Catalyst Tubes Removal and Reinstallation

Yara Tringen 2 Plant

Summary of Scope:

  • Radiant Section:
  • Replacement of 150Nos. Catalyst Tubes inclusive of inlet/outlet pigtails
  • 336Nos of Outlet Pigtail Replacement
  • Replace all spring supports on the Outlet Manifold
  • Furnace Walls:
  • Removal of Bottom Breaching Covers & Replace with new inclusive of panels & supports
  • Furnace Wall Replacement
  • Repairs all Broken Peep Doors
  • Re-install Arc Seal Blankets to prevent leakage between tube & boot

Safety and Commendations

  • Project was completed with zero incidents or accidents