NUIRON – SHUTDOWN WORKS
POLISHER REPAIR/SHUTDOWN WORKS
Summary of Scope:
- Prefabricate all diagonal plates
- Install 320pcs of diagonal plate to eliminate torsion whilst in production
- Remove and Replace pipe sections and RHS
- Install all diagonal and pipe sections
- Works performed on a 24hrs basis, 2x12hr shifts
- All welding done in accordance with AWS D1.1
Safety and Commendations
- Safety: Project was executed with Zero Accidents or Incidents.