NUIRON – SHUTDOWN WORKS

POLISHER REPAIR/SHUTDOWN WORKS

Summary of Scope:

  • Prefabricate all diagonal plates
  • Install 320pcs of diagonal plate to eliminate torsion whilst in production
  • Remove and Replace pipe sections and RHS
  • Install all diagonal and pipe sections
  • Works performed on a 24hrs basis, 2x12hr shifts
  • All welding done in accordance with AWS D1.1

Safety and Commendations

  • Safety: Project was executed with Zero Accidents or Incidents.